ANALYSING THE SIGNIFICANT INFLUENCES OF COST PERFORMANCE IN MALAYSIAN RAIL PROJECTS: EXPLORATORY FACTOR ANALYSIS
DOI:
https://doi.org/10.24191/myse.v11i1.993Keywords:
Construction Project Management, Construction Cost Management, Rail projects, Exploratory Factor Analysis (EFA)Abstract
Delivering successful rail projects has always been extremely difficult. The fact is widely discussed in developed nations as their outstanding rail networks were known to have significant cost overruns. A comprehensive rail network is progressing in developing nations, and cost overruns have already occurred in nations like China and India. The problem is critical in Malaysia, where poor cost performance has been highlighted for decades. This study aims to establish the significant influences on cost performance of rail projects, by assessing the critical influences that may affect project cost management. Primary data was gathered from 100 cost managers in the rail construction industry. Five (5) main component elements were discovered with a total of fifty (50) related items based on prior studies. Project estimation, project planning, project management, technical experience, and project complexity can be categorized as the primary component aspects. The influences and their respective items are then utilized to create the questionnaire for gathering data. Collected data were then analyzed using Exploratory Factor Analysis (EFA), which focused on the five (5) components and fifty (50) influences that affected rail construction cost performance. The overall variance percentage was 62.514%. Each component has a minimum of four variables, thus complying with the requisite that every component needs a minimum of three variables. The Kaiser-Meyer-Olkin (KMO) Measure of Sampling Adequacy value obtained from the results is 0.813, which is highly close to 1. All components satisfied the Factor Analysis standards as each influence loading is higher than 0.4. Project Planning has the highest Eigenvalue (26.764), while Project Estimation has the lowest Eigenvalue (5.136). Industry professionals need to understand the main elements affecting construction costs. Then the professionals can be empowered with the ability to develop effective strategies to improve cost management in rail projects.
References
Abbas, G., & Painting, N. (2017). Significant Factors Causing Cost Overruns in the Construction Industry in Afghanistan. Procedia Engineering, 182, 510–517. https://doi.org/10.1016/j.proeng.2017.03.145
Adam, A., Josephson, P. E. B., & Lindahl, G. (2017). Aggregation of Factors Causing Cost Overruns and Time Delays in Large Public Construction Projects: Trends and Implications. Engineering, Construction and Architectural Management, 24(3), 393–406. https://doi.org/10.1108/ECAM-09-2015-0135
Al-hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and Cost Overrun in Infrastructure Projects in Jordan. Procedia Engineering, 182, 18–24. https://doi.org/10.1016/j.proeng.2017.03.105
Alghonamy, A. (2015). Cost Overrun in Construction Projects in Saudi Arabia : Contractor s ‘ Perspective. International Journal of Engineering & Technology IJET-IJENS, 15(04).
Ali, A. S., & Kamaruzzaman, S. N. (2012). Cost Performance for Building Construction Projects in Klang Valley. Journal of Building Performance, 1(1 ).
Alsuliman, J. A. (2019). Causes of delay in Saudi public construction projects. Alexandria Engineering Journal, 58(2), 801–808. https://doi.org/10.1016/j.aej.2019.07.002
Andrić, J. M., Wang, J., & Zhong, R. (2019). Identifying the critical risks in railway projects based on fuzzy and sensitivity analysis: A case study of Belt and Road Projects. Sustainability (Switzerland), 11(5 ). https://doi.org/10.3390/su11051302
Apolot, R., & Tindiwensi, D. (2013). Investigation into the Causes of Delays and Cost Overruns in Uganda ’ s Public Sector Construction Projects. Journal of Construction Engineering, 18(2), 33–47. https://doi.org/10.5121/ijcsit.2011.3406
Asmi, A., Azis, A., Memon, A. H., & Rahman, I. A. (2013). Controlling Cost Overrun Factors in Construction Projects in Malaysia Controlling Cost Overrun Factors in Construction Projects in Malaysia. 5(September 2014), 2621–2629. https://doi.org/10.19026/rjaset.5.4706
Awojobi, O., & Jenkins, G. P. (2016). Managing the cost overrun risks of hydroelectric dams: An application of reference class forecasting techniques. Renewable and Sustainable Energy Reviews, 63, 19–32. https://doi.org/10.1016/j.rser.2016.05.006
Azman, N. S., Ramli, M. Z., & Zawawi, M. H. (2018). Factors affecting quality management of construction project using industrialized building system: A review. International Journal of Engineering and Technology(UAE), 7(4), 307–311. https://doi.org/10.14419/ijet.v7i4.35.22751
Bao, X. (2018). Urban Rail Transit Present Situation and Future Development Trends in China: Overall Analysis Based on National Policies and Strategic Plans in 2016–2020. Urban Rail Transit, 4(1), 1–12. https://doi.org/10.1007/s40864-018-0078-4
Belayutham, S., Mohamad Jaafar, R. N. A., Ismail, H. B., & Che Ibrahim, C. K. I. (2022). Production planning, monitoring and review: comparison between the practices in an urban rail transit megaproject with the Last Planner System. TQM Journal, 34(3), 515–533. https://doi.org/10.1108/TQM-11-2020-0282
Beria, P., Grimaldi, R., Albalate, D., & Bel, G. (2018). Delusions of Success: Costs and Demand of High-Speed Rail in Italy and Spain. Transport Policy, 68(September 2017), 63–79. https://doi.org/10.1016/j.tranpol.2018.03.011
Bujang, M. A., Omar, E. D., & Baharum, N. A. (2018). A review on sample size determination for cronbach’s alpha test: A simple guide for researchers. Malaysian Journal of Medical Sciences, 25(6), 85–99.
Business Times. (2012, May 21). Ipoh Padang Besar Rail Project Hits Snag? New Straits Times. https://www.klik.com.my/item/document/9473713/nst---mon-05-2012-business-times-210011-a-all
Cabuñas, J. T., & Silva, D. L. (2019). Exploratory factor-item analytic approach for construction project cost overrun using oblique promax rotation for predictors determination. International Journal of Innovative Technology and Exploring Engineering, 8(6), 47–54.
Cantarelli, C. C., Molin, E. J. E., Wee, B. Van, & Flyvbjerg, B. (2012). Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases. 22, 49–56 . https://doi.org/10.1016/j.tranpol.2012.04.001
Cantarelli, C. C., Van Wee, B., Molin, E. J. E., & Flyvbjerg, B. (2012). Different cost performance: Different determinants?. The case of cost overruns in Dutch transport infrastructure projects. Transport Policy, 22, 88–95. https://doi.org/10.1016/j.tranpol.2012.04.002
Cárdenas, I. C., Voordijk, H., & Dewulf, G. (2018). Beyond project governance. Enhancing funding and enabling financing for infrastructure in transport. Findings from the importance analysis approach. European Journal of Transport and Infrastructure Research (EJTIR), 18(4), 481–498.
Catalao, F. P., Cruz, C. O., & Sarmento, J. M. (2019). The determinants of cost deviations and overruns in transport projects , an endogenous models approach. Transport Policy, 74(December 2018), 224–238. https://doi.org/10.1016/j.tranpol.2018.12.008
Chandragiri, A. B., Hamim Jeelani, S., Akthar, S., & Lingeshwaran, N. (2021). A study and identification of the time and cost overrun in the construction project. Materials Today: Proceedings, 47(xxxx), 5426–5431. https://doi.org/10.1016/j.matpr.2021.06.268
Chen, Y., Ahiaga-Dagbui, D. D., Thaheem, M. J., & Shrestha, A. (2023). Toward a Deeper Understanding of Optimism Bias and Transport Project Cost Overrun. Project Management Journal, 54(5), 561–578. https://doi.org/10.1177/87569728231180268
Chevroulet, T., Giorgi, L., & Reynaud, C. (2012). New Approach for the Assessment of High-Speed Rail Projects and How to Contain Cost Overruns: Lessons from the EVA-TREN Project. Journal of Infrastructure Systems, 18(4), 297–304. https://doi.org/10.1061/(asce)is.1943-555x.0000111
Famiyeh, S., Amoatey, C. T., Adaku, E., Agbenohevi, C. S., Famiyeh, S., Amoatey, C. T., Adaku, E., Agbenohevi, C. S., Famiyeh, S., Amoatey, C. T., Adaku, E., & Agbenohevi, C. S. (2017). Major causes of construction time and cost overruns A case of selected educational sector projects in Ghana. Journal of Engineering, Design and Technology, 15(2), 181–198. https://doi.org/10.1108/JEDT-11-2015-0075
Flyvbjerg, B. (2014). Over Budget, Over Time, Over and Over Again: Managing Major Projects. April 2011. https://doi.org/10.1093/oxfordhb/9780199563142.003.0014
Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., Glenting, C., Holm, M. S., Lovallo, D., Lunn, D., Molin, E., Rønnest, A., Stewart, A., & van Wee, B. (2018). Five Things You Should Know About Cost Overrun. Transportation Research Part A: Policy and Practice, 118(July), 174–190. https://doi.org/10.1016/j.tra.2018.07.013
Gunduz, M., & Abdi, E. A. (2020). Motivational Factors and Challenges of Cooperative Partnerships between Contractors in the Construction Industry. Journal of Management in Engineering, 36(4), 04020018. https://doi.org/10.1061/(asce)me.1943-5479.0000773
Gunduz, M., & Maki, O. L. (2018). Assessing the risk perception of cost overrun through importance rating. Technological and Economic Development of Economy, 24(5), 1829–1844. https://doi.org/10.3846/20294913.2017.1321053
Hair, J. F., Babin, B. J., & Krey, N. (2017). Covariance-Based Structural Equation Modeling in the Journal of Advertising: Review and Recommendations. Rohrer College of Business Faculty Scholarship.
Hair, J. F., Risher, J. J., Sarstedt, M., & Ringle, C. M. (2019). When to use and how to report the results of PLS-SEM. European Business Review, 31(1), 2–24. https://doi.org/10.1108/EBR-11-2018-0203
Han, S. H., Yun, S., Kim, H., Kwak, Y. H., Park, H. K., & Lee, S. H. (2009). Analyzing schedule delay of mega project: Lessons learned from Korea train express. IEEE Transactions on Engineering Management, 56(2), 243–256. https://doi.org/10.1109/TEM.2009.2016042
Hanif, H., Khurshid, M. B., Lindhard, S. M., & Aslam, Z. (2016). Impact of variation orders on time and cost in mega hydropower projects of Pakistan. Journal of Construction in Developing Countries, 21(2), 37–53. https://doi.org/10.21315/jcdc2016.21.2.3
Hetemi, E., Gemünden, H. G., & Meré, J. O. (2020). Embeddedness and Actors’ Behaviors in Large-Scale Project Life Cycle: Lessons Learned from a High-Speed Rail Project in Spain. Journal of Management in Engineering, 36(6), 05020014. https://doi.org/10.1061/(asce)me.1943-5479.0000849
Hussain, O. A. I., Moehler, R. C., Walsh, S. D. C., & Ahiaga-Dagbui, D. D. (2023). Minimizing Cost Overrun in Rail Projects through 5D-BIM: A Systematic Literature Review. Infrastructures, 8(5), page number?. MDPI. https://doi.org/10.3390/infrastructures8050093
Hutchinson, F. E. (2016). The Kuala Lumpur-Singapore High Speed Rail: Costs, Contracts, and Complications. ISEAS Perspective, 7, 1–11.
Invernizzi, D. C., Locatelli, G., & Brookes, N. J. (2017). Cost overruns - Helping to define what they really mean. Proceedings of the Institution of Civil Engineers: Civil Engineering, 171(2), 85–90. https://doi.org/10.1680/jcien.17.00001
Joshi, A., Kale, S., Chandel, S., & Pal, D. (2015). Likert Scale: Explored and Explained. British Journal of Applied Science & Technology, 7(4), 396–403. https://doi.org/10.9734/bjast/2015/14975
Kim, S., Tuan, K. N., Lee, J. Do, Pham, H., & Luu, V. T. (2017). Cost Overrun Factor Analysis for Hospital Projects in Vietnam. KSCE Journal of Civil Engineering, 00(0000), 1–11. https://doi.org/10.1007/s12205-017-0947-5
Lee, C., & Chew-ging, L. (2017). The Evolution of Development Planning in Malaysia. 34(3), 436–461. https://doi.org/10.1355/ae34-3b
Lee, J., Kim, K., & Oh, J. (2022). Build-Transfer-Operate with risk sharing approach for railway public-private-partnership project in Korea. Asian Transport Studies, 8(January), 100061. https://doi.org/10.1016/j.eastsj.2022.100061
Lee Yuk, P. (2009, November 6). RM6bil Ipoh-Rawang track plan has cost overrun reaching RM1.14bil. The Star. https://www.thestar.com.my/news/nation/2009/11/06/rm6bil-ipohrawang-track-plan-has-cost-overrun-reaching-rm114bil
Locatelli, G., Invernizzi, D. C., & Brookes, N. J. (2017). Project characteristics and performance in Europe: An empirical analysis for large transport infrastructure projects. Transportation Research Part A: Policy and Practice, 98, 108–122. https://doi.org/10.1016/j.tra.2017.01.024
Love, P. E. D., Ahiaga-Dagbui, D., Welde, M., & Odeck, J. (2017). Light rail transit cost performance: Opportunities for future-proofing. Transportation Research Part A: Policy and Practice, 100, 27–39. https://doi.org/10.1016/j.tra.2017.04.002
Lu, W., Hua, Y., & Zhang, S. (2017). Logistic Regression Analysis for Factors Influencing Cost Performance of Design-Bid-Build and Design-Build Projects. Engineering, Construction and Architectural Management, 24(1), 118–132. https://doi.org/10.1108/ECAM-07-2015-0119
Memon, A. H., & Rahman, I. A. (2014). SEM-PLS analysis of inhibiting factors of cost performance for large construction projects in malaysia: Perspective of clients and consultants. The Scientific World Journal, . https://doi.org/10.1155/2014/165158
Mevada, J., & Devkar, G. (2017). Analysis of Reasons for Cost and Time Overrun in Indian Megaprojects. MATEC Web of Conferences, 120(2017), 1–10. https://doi.org/10.1051/matecconf/201712002018
Ministry of Transport Malaysia; (2022). New Rail Projects. https://www.mot.gov.my/en/land/development/new-rail-projects
Mohammad, M. F., Baharin, A. S., Musa, M. F., & Yusof, M. R. (2016). The Potential Application of IBS Modular System in the Construction of Housing Scheme in Malaysia. Procedia - Social and Behavioral Sciences, 222, 75–82. https://doi.org/10.1016/j.sbspro.2016.05.189
Mohammad, S., Tabatabaei, M., Taabayan, P., Hashemi, A. M., & Willoughby, K. (2016). Studying the Reasons for Delay and Cost Overrun in Construction Projects : The Case of Iran. Journal of Construction in Developing Countries, 21(1), 51–84. https://doi.org/10.21315/jcdc2016.21.1.4
Mohd Kamar, I. F., Che Ahmad, A., & Mohamad Derus, M. (2017). Overview of Safety & Health Cost Framework for the Construction of Rail Infrastructure Projects. In Malaysian Journal of Sustainable Environment, 2(1), . 101 - ?. https://doi.org/10.24191/myse.v2i1.5586
Molinari, L., Haezendonck, E., & Mabillard, V. (2023). Cost overruns of Belgian transport infrastructure projects: Analyzing variations over three land transport modes and two project phases. Transport Policy, 134, 167–179. https://doi.org/10.1016/j.tranpol.2023.02.017
Muhamad, N. H., & Mohammad, M. F. (2018). IMPACT OF DESIGN CHANGES IN CONSTRUCTION PROJECT. Malaysian Journal of Sustainable Environment, volume and issue?, 1–18.
Nik Mohd Ainul Azman, N. N. K., Che Ahmad, A., Mohd Derus, M., & Mohd Kamar, I. F. (2018). Accident Cost Ratio of Bodily Injury in Railway Construction Projects. Malaysian Journal of Sustainable Environment, 5(2), 75. https://doi.org/10.24191/myse.v5i2.5618
Office of The Premier of Sarawak. (2023). Premier: Proposed Trans Borneo Railway a boon to northern Sarawak. https://premier.sarawak.gov.my/web/subpage/news_view/5481
Olatunji, O. A., Orundami, A. O., & Ogundare, O. (2018). Causal Relationship Between Material Price Fluctuation and Project’s Outturn Costs. Built Environment Project and Asset Management, 8(4), 358–371. https://doi.org/10.1108/BEPAM-12-2017-0119
Olawale, Y., & Sun, M. (2015). Construction project control in the UK: Current practice, existing problems and recommendations for future improvement. International Journal of Project Management, 33(3), 623–637. https://doi.org/10.1016/j.ijproman.2014.10.003
Omotayo, T. S., Awuzie, B., Obi, V. K., Ajayi, S., Obi, L. I., Osobajo, O., & Oke, A. (2022). The System Dynamics Analysis of Cost Overrun Causations in UK Rail Projects in a COVID-19 Epidemic Era. SAGE Open, 12(2). https://doi.org/10.1177/21582440221097923
Osei-kyei, R., & Chan, A. P. C. (2017). Review of studies on the Critical Success Factors for Public – Private ScienceDirect Review of studies on the Critical Success Factors for Public – Private Partnership ( PPP ) projects from 1990 to 2013. JPMA, March 2015. https://doi.org/10.1016/j.ijproman.2015.02.008
Pallant, J. (2020). SPSS Survival Manual: A step by step guide to data analysis using IBM SPSS. 6th ed. McGraw-Hill Education, Routledge: place of published?
Park, Y. I., & Papadopoulou, T. C. (2012). Causes of Cost Overruns in Transport Infrastructure Projects in Asia: Their Significance and Relationship with Project Size. Built Environment Project and Asset Management, 2(2), 195–216. https://doi.org/10.1108/20441241211280873
Pickrell, D. H. (1992). A desire named streetcar: fantasy and fact in rail transit planning. Journal of the American Planning Association, 58 (2), 15.
Plebankiewicz, E., & Wieczorek, D. (2020). Prediction of cost overrun risk in construction projects. Sustainability (Switzerland), 12(22), 1–15. https://doi.org/10.3390/su12229341
Prasetijo, J., Baba, I., Hasnan, K., Ismail, S., Anuar, M. A. R. K., Aron, M. A. M., Setiawan, M. I., & Mudjanarko, S. W. (2019). Modelling rail accident and incident causes by using zero-inflated poisson approach. International Journal of Integrated Engineering, 11(3), 255–263. https://doi.org/10.30880/ijie.2019.11.03.27
Rahn, M. (2014). When are factor loadings not strong enough? Factor Analysis: A Short Introduction, Part 5–Dropping Unimportant Variables from Your Analysis. https://www.theanalysisfactor.com/factor-analysis-5/
Sadullah, M., Ghazali, M., & Rashid, A. (2018). Critical success factors in a public–private partnership highway project in Malaysia: Ampang–Kuala Lumpur elevated highway. Proceedings of Institution of Civil Engineers: Management, Procurement and Law, 170(6), 234–242. https://doi.org/10.1680/jmapl.16.00034
Saleh, A., & Bista, K. (2017). Examining Factors Impacting Online Survey Response Rates in Educational Research: Perceptions of Graduate Students. Journal of MultiDisciplinary Evaluation, 13(29), 63–74.
Samuels, P. (2016). Advice on Exploratory Factor Analysis. Centre for Academic Success, Birmingham City University, June, 2. https://doi.org/10.13140/RG.2.1.5013.9766
Samwel, M. C., Wang, D., Shaldon, L. S., & Obadia, K. B. (2018). Influence of technology transfer on performance and sustainability of standard gauge railway in developing countries. Technology in Society. https://doi.org/10.1016/j.techsoc.2018.09.007
Sarmento, J. M., & Renneboog, L. (2017). Cost Overruns in Public Sector Investment Projects. Public Works Management & Policy, 22(2), 140–164. https://doi.org/10.1177/1087724X16668357
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014). Cost overrun in the Malaysian construction industry projects: A deeper insight. International Journal of Project Management, 32(8), 1471–1480. https://doi.org/10.1016/j.ijproman.2014.04.004
Shi, F. (2015). Study on a stratified sampling investigation method for resident travel and the sampling rate. Discrete Dynamics in Nature and Society, 2015. https://doi.org/10.1155/2015/496179
Shibani, D. A. (2015). Time and Cost Overrun in Construction Projects in Egypt Time and Cost Overrun in Construction Projects in Egypt. September, 22–29.
Tee Lin, S. (2012). PDP to bear MRT cost overruns of over 15%. The Star. https://www.thestar.com.my/business/business-news/2012/02/09/pdp-to-bear-mrt-cost-overruns-of-over-15
The Sun Daily. (2015). AG’s Report 2015: ERL Extension from KLIA to KLIA2 incurred a RM29m budget overrun. https://www.thesundaily.my/archive/1806581-HSARCH368070
Ullah, K., Abdullah, A. H., Nagapan, S., Suhoo, S., & Khan, M. S. (2017). Theoretical Framework of the Causes of Construction Time and Cost Overruns. IOP Conference Series: Materials Science and Engineering, 271(1). https://doi.org/10.1088/1757-899X/271/1/012032
Vaardini, U. S., Karthiyayini, S., & Ezhilmathi, P. (2016). Study On Cost Overruns in Construction Projects –A Review. International Journal of Applied Engineering Research, 11(3), 356–363.
Venkatesh, P. K., & Venkatesan, V. (2017). Delays in construction projects: A review of causes, need and scope for further research. Malaysian Construction Research Journal, 23(3), 89–113.
Venkateswaran, C. B., & Murugasan, R. (2017). Time Delay and Cost Overrun of Road over Bridge ( ROB ) Construction Projects in India. Journal of Construction in Developing Countries, 22(November), 79–96.
Watkins, M. W. (2018). Exploratory Factor Analysis: A Guide to Best Practice. Journal of Black Psychology, 44(3), 219–246. https://doi.org/10.1177/0095798418771807
Xu, W. A., & Huang, Y. (2019). The correlation between HSR construction and economic development – Empirical study of Chinese cities. Transportation Research Part A, 126(May), 24–36. https://doi.org/10.1016/j.tra.2019.05.017
Zafar, I., Yousaf, T., & Ahmed, D. S. (2016). Evaluation of Risk Factors Causing Cost Overrun in Road Projects in Terrorism Affected Areas Pakistan – A Case Study. KSCE Journal of Civil Engineering, 20(5), 1613–1620. https://doi.org/10.1007/s12205-015-0348-6
Zhang, B., Le, Y., Xia, B., & Skitmore, M. (2017). Causes of business-to- government corruption in the tendering process in China. J. Manage. Eng. 33 (2): 05016022. https://doi.org/https://doi.org/10.1061/(ASCE)ME.1943-5479 .0000479
Zhu, Z., Zhu, Y., Liu, R., Zhang, L., & Yuan, J. (2022). Examining the Effect of Urban Rail Transit on Property Prices from the Perspective of Sustainable Development : Evidence. Buildings, 12, 1760. https://doi.org/https://doi.org/10.3390/buildings12101760
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Malaysian Journal of Sustainable Environment
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Open Access is by licensing the content with a Creative Commons (CC) license.
Malaysian Journal of Sustainable Environment by MySE is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Based on a work at https://myse.my.
Permissions beyond the scope of this license may be available at https://creativecommons.org/choose/#metadata.
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License