Developing a Resilient Crisis Management Plan (CMP) for the Malaysian Construction Sector

Authors

  • Anis Mardhiah Mukhtar Faculty of Architecture, Planning and Surveying, Universiti Teknologi MARA, Shah Alam, Selangor MALAYSIA
  • Rumaizah Mohd Nordin Faculty of Architecture, Planning and Surveying, Universiti Teknologi MARA, Shah Alam, Selangor MALAYSIA
  • Norfashiha Hashim Faculty of Architecture, Planning and Surveying, Universiti Teknologi MARA, Shah Alam, Selangor MALAYSIA
  • Abdul Aziz Abas Ranhill Bersekutu Sdn Bhd, Suite 2302 Level 2 Plaza Permata, No. 6 Jalan Kampar, Off Jalan Tun Razak Kuala Lumpur, MALAYSIA

Keywords:

Crisis, External Crisis, Crisis Management Plan, Construction Sector

Abstract

Construction is a diverse and complex sector. It consists of projects with intricate activities and interfaces between stakeholders who undergo a series of development phases using numerous resources, integration of technologies, materials, and approaches. Theoretically, construction projects can be well planned. However, it is being exposed to unanticipated events or crises that could disrupt original plans, affecting organizations’ operation and progress of construction projects. Problems may even have the propensity to destroy the organization significantly. Considering the current paradigm of crisis, the Covid-19 outbreak that emerged in late 2019 has continuously left a lasting impact on the construction industry. As of August 2020, Covid-19 has spread to over 200 countries, and the number has increased beyond 100,000 cases in Malaysia. Regardless of Covid-19 has placed great stress on all aspects worldwide, it led to the closure of most construction businesses, causing contraction towards industry growth to the greatest to extend of -7.9%, the lowest since 1999. In this context, the effort to ensure the preparedness of the construction organizations against crisis has become an issue. Hence, this paper aims to structure a framework that consists of principles and processes which can recover and develop a resilient construction industry. The method used for this study is Systematic Literature Review of related journals gathered through WOS, ScienceDirect, and Google Scholar, reports, and relevant references from Government Authorised agencies circa 1998 to 2020. 4262 articles were identified, and 111 papers were subsequently selected for further analysis. Based on the findings, there are five major phases of CM, including prepare, prevent, respond, evaluate, and redesign. The proposed CM includes 4 elements and 2 outputs. The preliminary findings form the foundation for an extended investigation to offer a specific crisis management plan to guide the Malaysian construction industry, specifically in Klang Valley, to be resilient during plight.

References

Anthopoulos, L. G., Kostavara, E., & Pantouvakis, J.-P. (2013). An Effective Disaster Recovery Model for Construction Projects. Procedia - Social and Behavioral Sciences, 74, 21–30.

Babu, S. S., & Sudhakar. (2016). Construction Project Management During Economic Crisis. International Journal of Management (IJM), 370-382

Bakar, A. H., & Awang, A. (2011). Strategies for Survival during Economic Downturn in Construction Industry: A Survey on Construction Companies in Malaysia. World Applied Science Journal, 1967-1974.

Bank Negara Malaysia. (2020). Economic and Financial Developments in Malaysia in the Second Quater of 2020. Kuala Lumpur: Bank Negara Malaysia.

Bernama . (2020, April 2). Most companies have crisis management plan. Retrieved from The Star.

Biörck, J., Blanco, J. L., & J. M. (2020). How construction can emerge stronger after coronavirus. Mckinsey Engineering, 1-28.

Boin, A., & Hart, P. ‘. (2003). The Crisis Approach. London: Springer Link.

Boin, A., & Hart, P. ‘. (2005). The Politics of Crisis Management: Public Leadership under Pressure. New York: Cambridge University Press

Boin, A. (2010). Managing Transboundary Crises: Identifying the Building Blocks of an Effective Response System. Blackwell Publishing.

Bundy, J., Pfarrer, D.M. (2017). Crises and Crisis Management: Integration, Interpretation, and Research Development. Journal of Management, 1661-1692.

CIDB. (2017). Country Reports Malaysia. 22nd Asia Construct Conference. Seoul, Korea: Construction Industry Development Board

CIDB. (2020). Leadership in the time of Pandemic. Kuala Lumpur: Construction Industry Development Board.

Coombs, W. (2014). Ongoing crisis communication: Planning, managing, and responding. Sage Publications.

DOSM. (2018) Annual Economic Statistic 2018: Construction. Putrajaya: Department of Statistic Malaysia

DOSM. (2020). Malaysia Economic Statistic Review. Putrajaya: Department of Statistic Malaysia.

ILO. (2020). The socioeconomic impacts of COVID-19 in Malaysia: Policy review and guidance for protecting the most vulnerable and supporting enterprises. Kuala Lumpur:

Filho, W.L., & Brandli, L.L., (2020). Covid-19 and the UN Sustainable Development Goals: Threat to Solidarity or an Opportunity?. MDPI, 1-14.

Gamil, Y., & Alhagar, A. (2020). The Impact of Pandemic Crisis on the Survival of Construction Industry: A Case of COVID-19. Mediterranean Journal of Social Sciences, 122-130.

Glaesser, D., (2006).Crisis Management in the Tourism Industry (2nd ed). Oxford: Butterworths-Heinmann

Jose, J. (2019). Crisis Manageemnt in Construction Projects. International Research Journal of Engineering and Technology (IRJET), 1892-1896

Khan, R. A., Liew, M. S., & Ghazali, Z. Bin. (2014). Malaysian Construction Sector and Malaysia Vision 2020: Developed Nation Status. Procedia - Social and Behavioral Sciences, 109, 507–513. https://doi.org/10.1016/j.sbspro.2013.12.498

Lockwood, N. R. (2005). Crisis management in today’s business environment: HR’s

strategic role. SHRM Research Quarterly. Retrieved March 5, 2007, from www.shrm.org/hrmagazine.

Mark, S., & Lewis, P. (2012). Research Methods for Business Students. London: Prentice Hall.

Mikusova. M., & Horvathova. P. (2019). Prepared for a Crisis? Basic Elements of Crisis Management in an Organization. Economic Research, 1844-1868.

MIDA. (2020). Impact of COVID-19 on the Malaysian Economy and the Mitigation Measures. Kuala Lumpur: Malaysian Investment Development Authority.

Mohamed, E. (2020). Covid-19: Analysis of the Situation for the Construction Sector in Malaysia. Kuala Lumpur: Universiti Islam Antarabangsa

Murad, M. A. (2019). Turnover Culture and Crisis Manageemnt: Insights from malaysian Hotel industry. Academy of Strategic Management, 1544-1548.

Newman, P. (2020). Covid, Cities and Climate: Historical Precedents and Potential Transitions for the New Economy. MDPI, 1-29.

Ozcan. (2015). Ozcan 2015. Philosophy, 93(96), 241. http://eprints.soton.ac.uk/158357/

Papanti et al. (2013). Spiceophrenia": a systematic overview of "spice"-related psychopathological issues and a case report.ResearchGate, 379-389.

Pinheiro, M.D., & Luis, N.C. (2020). Covid-19 Could Leverage a Sustainable Built Environment. MDPI,1-27

Rajprasad, & Thamilarasu. (2018). Role of Crisis Management in Construction Projects. International Journal of Engineering & Technology, 451-453.

Ramli, R. (2020, May 6). GHR Post. Preparing for post-COVID-19 from the lens of SDGs: Insight from Malaysia.

Sahin, S., & Ulubeyli, S. (2015). Innovative Crisis Management in Construction: Approaches and the Process. ScienceDirect, 2299-2305.

Salim. (2020). COVID-19 epidemic in Malaysia: Impact of lock-down on infection dynamics. ResearchGate, 1-28.

ScienceDirect (SD). Available online: https://www.sciencedirect.com/ (accessed on 5 June 2020).

Sfakianaki, E., Iliadis, T., & Zafeiris, E. (2015). Crisis management under an economic recession in construction: The Greek case. International Journal of Management and Decision Making, 14(4), 373–389. https://doi.org/10.1504/IJMDM.2015.074015

Shammi, M. (2020). Strategic assessment of COVID-19 pandemic in Bangladesh: comparative lockdown scenario analysis, public perception,and management for sustainability. Springer Nature, 1-44.

Srinivasan, N., & Nandhini, N. (2015). A Study on Crisis Management in Construction Projects. International Journal of Innovative Research in Science, Engineering and Technology, 9965-9967.

t' Hart, P., (1993). Symbols, Rituals and Power: The Lost Dimensions of Crisis Management. Journal of of Contingencies and Crisis Management, 36-50

The World Bank (1984). The Construction Industry: Issues and Strategies in Developing Countries. Washington D.C.: The World Bank

UNDP. (2017). Framework for Resilient Development in the Pacific: An Integrated Approach to Address Climate Change and Disaster Risk Management (FRDP) 2017–2030. Fiji: UNDP.

United Nations. (2020). A UN Framework for the immediate Socio-economic Response to Covid-19. New York: United Nations

Victor, M. (2020). Crisis Management Framework: COVID-19 Crisis Response Checklist. Deloitte.

Walsh. (2020, June 18). A tidal wave of bankruptcies is coming. Retrieved from https://www.nytimes.com/2020/06/18/business/corporate-bankruptcy-

Web of Science (WoS). Available online: https://login.webofknowledge.com/ (accessed on 5 June 2020).

Wenzel, M., Kramer, H., & Koch, J. (2020). Mind the gap: How organizational actors cope with an identity–strategy misalignment. Strategic Organization, 212-244.

WHO. (2020). Covid-19:Strategy Updates. New York: World Health Organization.

World Bank Group. (2020). The Impact of Covid-19 on the Water and Sanitation Sector. New York: World Bank Group.

Zhang-Zhang, Y., & Varma, A. (2020, August 23). European Business Review. Retrieved from Organization Preparedness with Covid-19 Strategies Planning and Human Creativity: https://www.europeanbusinessreview.com/organizational-preparedness-with-covid-19-strategic-planning-and-human-creativity/

Downloads

Published

16-07-2025

How to Cite

Mukhtar, A. M. ., Mohd Nordin, R. ., Hashim, N. ., & Abas, A. A. . (2025). Developing a Resilient Crisis Management Plan (CMP) for the Malaysian Construction Sector. Built Environment Journal, 19(1). Retrieved from https://journal.uitm.edu.my/ojs/index.php/BEJ/article/view/7558